Free CCM Practice Questions

10 free, exam-style Certified Construction Manager (CCM) practice questions with answers and explanations. No signup required. Work through them below, then take the full free CCM practice test to study every exam domain.

The CCM exam has 180 questions and runs 4 hours.

These 10 free CCM questions are organized by exam domain, so you can see how each part of the Certified Construction Manager blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Project Management Planning 15% of exam

Question 1

A public university wants a construction manager to provide preconstruction advice during design and then hold the trade contracts and deliver the project under a guaranteed maximum price. Which project delivery approach is the university procuring?

  1. CM-at-Risk under a guaranteed maximum price
  2. Agency CM, providing professional services for a fee
  3. Design-build, combining design and construction in one entity
  4. Multiple-prime contracts managed directly by the owner
Show answer & explanation

Correct answer: A - CM-at-Risk under a guaranteed maximum price

Domain 2: Cost Management 15% of exam

Question 2

When establishing the owner's total project budget, the construction manager separates the cost of construction (hard cost) from soft costs. Which of the following is part of the cost of construction rather than a soft cost?

  1. Building permit and plan-review fees
  2. Installed mechanical, electrical, and plumbing systems
  3. The construction manager's professional fee
  4. Owner's project financing and loan interest carrying costs
Show answer & explanation

Correct answer: B - Installed mechanical, electrical, and plumbing systems

Domain 3: Time Management 10% of exam

Question 3

On a CPM network, Activity D has an early start of day 8, an early finish of day 12, a late start of day 15, and a late finish of day 19. What is the total float of Activity D?

  1. 0 days
  2. 4 days
  3. 7 days
  4. 11 days
Show answer & explanation

Correct answer: C - 7 days

Domain 4: Quality Management 10% of exam

Question 4

During excavation, a contractor encounters subsurface rock at a depth where the contract's geotechnical boring logs indicated only soil, and promptly notifies the construction manager. This is BEST characterized as:

  1. A Type II differing site condition
  2. A force majeure event
  3. A constructive change
  4. A Type I differing site condition
Show answer & explanation

Correct answer: D - A Type I differing site condition

Domain 5: Contract Administration 10% of exam

Question 5

On a project under an agency CM arrangement, the contractor inspects and tests its own installed work for conformance, and the construction manager reviews and audits that program on the owner's behalf. The construction manager's activity is BEST described as:

  1. Quality assurance
  2. Quality control
  3. Quality management
  4. Commissioning
Show answer & explanation

Correct answer: A - Quality assurance

Domain 6: Safety Management 5% of exam

Question 6

Under OSHA's Multi-Employer Citation Policy, a general contractor that has general supervisory authority over a worksite - including the power to correct hazards or require others to correct them - is MOST likely to be cited as the:

  1. Creating employer
  2. Controlling employer
  3. Exposing employer
  4. Correcting employer
Show answer & explanation

Correct answer: B - Controlling employer

Domain 7: Professional Practice 10% of exam

Question 7

A project carries the risk of financial loss if the contractor fails to complete the work, so the owner requires the contractor to furnish a performance bond. In risk-management terms, requiring the bond is an example of which response strategy?

  1. Risk avoidance
  2. Risk mitigation
  3. Risk transfer
  4. Risk acceptance
Show answer & explanation

Correct answer: C - Risk transfer

Domain 8: Sustainability, Resilience, and Risk Management 5% of exam

Question 8

A construction manager serving as the owner's agent is privately offered a paid consulting engagement by a subcontractor that is currently bidding on the same project. Under the CMAA Code of Professional Conduct, the construction manager's MOST appropriate action is to:

  1. Accept the engagement, since it is unrelated to the bid
  2. Accept only if the consulting fee is below a nominal threshold
  3. Evaluate the subcontractor's bid first, then decide
  4. Decline or disclose the conflict of interest to the owner
Show answer & explanation

Correct answer: D - Decline or disclose the conflict of interest to the owner

Domain 9: Building Information Modeling / Digital Practices 5% of exam

Question 9

An agency is delivering a major water-conveyance and pump-station infrastructure project and wants a third-party sustainability rating suited to the project type. Which rating system is specifically designed for sustainable infrastructure?

  1. Envision
  2. LEED
  3. Green Globes
  4. ENERGY STAR
Show answer & explanation

Correct answer: A - Envision

Domain 10: Program Management 15% of exam

Question 10

Early in design, the construction manager uses the project's building information model to identify physical conflicts between the structural framing and the mechanical ductwork before they are built. This specific use of BIM is known as:

  1. 4D modeling
  2. Clash detection
  3. Quantity takeoff
  4. Value engineering
Show answer & explanation

Correct answer: B - Clash detection