10 free, exam-style Certified Construction Manager (CCM) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free CCM practice test to study every exam domain.
These 10 free CCM questions are organized by exam domain, so you can see how each part of the Certified Construction Manager blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Project Management Planning 15% of exam
Question 1
A public university wants a construction manager to provide preconstruction advice during design and then hold the trade contracts and deliver the project under a guaranteed maximum price. Which project delivery approach is the university procuring?
- CM-at-Risk under a guaranteed maximum price
- Agency CM, providing professional services for a fee
- Design-build, combining design and construction in one entity
- Multiple-prime contracts managed directly by the owner
Show answer & explanation
Correct answer: A - CM-at-Risk under a guaranteed maximum price
Domain 2: Cost Management 15% of exam
Question 2
When establishing the owner's total project budget, the construction manager separates the cost of construction (hard cost) from soft costs. Which of the following is part of the cost of construction rather than a soft cost?
- Building permit and plan-review fees
- Installed mechanical, electrical, and plumbing systems
- The construction manager's professional fee
- Owner's project financing and loan interest carrying costs
Show answer & explanation
Correct answer: B - Installed mechanical, electrical, and plumbing systems
Domain 3: Time Management 10% of exam
Question 3
On a CPM network, Activity D has an early start of day 8, an early finish of day 12, a late start of day 15, and a late finish of day 19. What is the total float of Activity D?
- 0 days
- 4 days
- 7 days
- 11 days
Show answer & explanation
Correct answer: C - 7 days
Domain 4: Quality Management 10% of exam
Question 4
During excavation, a contractor encounters subsurface rock at a depth where the contract's geotechnical boring logs indicated only soil, and promptly notifies the construction manager. This is BEST characterized as:
- A Type II differing site condition
- A force majeure event
- A constructive change
- A Type I differing site condition
Show answer & explanation
Correct answer: D - A Type I differing site condition
Domain 5: Contract Administration 10% of exam
Question 5
On a project under an agency CM arrangement, the contractor inspects and tests its own installed work for conformance, and the construction manager reviews and audits that program on the owner's behalf. The construction manager's activity is BEST described as:
- Quality assurance
- Quality control
- Quality management
- Commissioning
Show answer & explanation
Correct answer: A - Quality assurance
Domain 6: Safety Management 5% of exam
Question 6
Under OSHA's Multi-Employer Citation Policy, a general contractor that has general supervisory authority over a worksite - including the power to correct hazards or require others to correct them - is MOST likely to be cited as the:
- Creating employer
- Controlling employer
- Exposing employer
- Correcting employer
Show answer & explanation
Correct answer: B - Controlling employer
Domain 7: Professional Practice 10% of exam
Question 7
A project carries the risk of financial loss if the contractor fails to complete the work, so the owner requires the contractor to furnish a performance bond. In risk-management terms, requiring the bond is an example of which response strategy?
- Risk avoidance
- Risk mitigation
- Risk transfer
- Risk acceptance
Show answer & explanation
Correct answer: C - Risk transfer
Domain 8: Sustainability, Resilience, and Risk Management 5% of exam
Question 8
A construction manager serving as the owner's agent is privately offered a paid consulting engagement by a subcontractor that is currently bidding on the same project. Under the CMAA Code of Professional Conduct, the construction manager's MOST appropriate action is to:
- Accept the engagement, since it is unrelated to the bid
- Accept only if the consulting fee is below a nominal threshold
- Evaluate the subcontractor's bid first, then decide
- Decline or disclose the conflict of interest to the owner
Show answer & explanation
Correct answer: D - Decline or disclose the conflict of interest to the owner
Domain 9: Building Information Modeling / Digital Practices 5% of exam
Question 9
An agency is delivering a major water-conveyance and pump-station infrastructure project and wants a third-party sustainability rating suited to the project type. Which rating system is specifically designed for sustainable infrastructure?
- Envision
- LEED
- Green Globes
- ENERGY STAR
Show answer & explanation
Correct answer: A - Envision
Domain 10: Program Management 15% of exam
Question 10
Early in design, the construction manager uses the project's building information model to identify physical conflicts between the structural framing and the mechanical ductwork before they are built. This specific use of BIM is known as:
- 4D modeling
- Clash detection
- Quantity takeoff
- Value engineering
Show answer & explanation
Correct answer: B - Clash detection